Military Ridge Path & Cannonball Path detours are planned to start next Monday, December 7, 2020. Portions of these paths, including the Velo UnderRound roundabout, will be closed during the project. To download the detour map or for more information visit: https://link.madsewer.org/NSVI
Madison Metropolitan Sewerage District is replacing the existing interceptor along the Military Ridge Trail and Cannonball Path between McKee Road and Dunn’s Marsh. This project, known as Nine Springs Valley Interceptor Improvements - McKee Road to Dunn's Marsh, will protect public health by replacing deteriorated infrastructure and increase capacity to serve growing communities. Work is anticipated to begin December 7, 2020 and be complete December 2021.
For next week, for both the northern & southern portions anticipate some clearing & grubbing (removing select shrubs and trees), erosion control being installed, and the asphalt being pulverized (will be broken up). The contractor anticipates starting on the northern portion of the project with pipe. That would be the western portion of Dunn’s Marsh and working their way back southwest along the trail towards Discovery Drive with pipe installation.